Water - Steam Line Flushing














To reach water quality as mention on http://www.anto-hendarto.blogspot.com/2009/10/water-quality.html, after the outage, need several steps as below.


First step is getting a good turbidity and low TSS. Second step after firing is making a good pH by ammonia dosing but still be monitored the conductivity. Also oxygen content need to reduced by opening de-aerator venting valve widely.
















































After the unit get synchronize to grid, our target is going to make a save operation by running the unit with 50% load following with purging the silica. Usually need 12h to get a good water quality for example low silica and low specific conductivity.

After the water quality reach, the unit ready to full load.