Thursday, July 3, 2014

Buchholz Relay Alarm Part 5

Please visit Buchholz Relay Alarm Part 4 for previous explanation.
This is the schedule of Transformer test but unfortunately we don't have all the result.




Preparation: Isolated, Install scaffold, install portable grounding, disconnect HV & LV Bushing


SFRA test theory, please visit http://anto-hendarto.blogspot.com/2014/03/sweep-frequency-response-analysis.html

DFR test theory, please visit http://anto-hendarto.blogspot.com/2014/04/dielectric-frequency-responce_3.html

Turn Transformer Ratio Test.
The performance of a transformer largely depends upon perfection of specific turns or voltage ratio of transformer.

Turn Ratio test theory, please visit http://anto-hendarto.blogspot.com/2014/04/transformer-ratio-test.html





continue to Buchholz Relay Alarm Part 6